Air Pressure & Ventilation Testing + SAPs

THE BRIEF

  • The property located in Thorpe Satchville 
  • Two Air Tests were performed due to the first failing. However, thanks to our team we were able to identify and fix issues so the second test resulted in a pass
Air Pressure & Ventilation Testing + SAPs

THE PROCESS

  • After reviewing drawings, on site testing was ready to be completed. In accordance with our strict air tightness testing procedures, all calibrated equipment was setup to ensure the most accurate result possible
  • Our Consultants guided the team on-site here in order to pass their SAPs. This was achieved with advice and recommendations

THE RESULTs

  • AIR TESTING RESULTS

≤ 10.0 m³.h.m² @ 50pa

Target

  • SAP CALCULATION RESULTS

≤ 25.68

Target Emission Rate (TER)

≤ 60.30

Target Fabric Energy Efficiency (TFEE)

8.60

Result

19.54

Dwelling Emission Rate (DER)

55.70

Dwelling Fabric Energy Efficiency (DFEE)

PASS

PASS

PASS

  • Compliant

Please refer to our Myth Busters for SAP Calculations here, Myth Busters for Air Tightness Testing here for common misconceptions and our How To Guides in our Advice Centre here

Start Using UK Building Compliance Today


You may also like

January 25, 2024

July 12, 2022

June 27, 2022

June 23, 2022

May 17, 2022

May 12, 2022

Start Using UK Building Compliance Today