Air Pressure Testing Buckingham

Project: Air Pressure Testing Willenhall

Air Pressure Testing Willenhall

Completed: 26/07/2018

Technician: Cameron Milne

The Brief

We were instructed to complete 4 domestic Air Pressure tests on these new-build houses in Willenhall

The required targets for each test were: 4.9

The Process

After reviewing drawings, on site testing was ready to be completed. All suitable equipment was set up and checked over to ensure the best possible result.

The Result

 

Target

Target

Target

Target

Result

Result

Result

Result

 

Pass

 

Pass

 

Pass

 

Pass

The Outcome

This buildings passed the Air Pressure Tests and as a result, certificates will be issued shortly.

For more information on what is required to pass an Air tightness test click HERE