Project: Air Pressure Testing Ullesthorpe LE17

Air Pressure Testing Ullesthorpe LE17

Completed: 4/1/2018

Technician: Cameron Milne

The Brief

We were instructed to complete two Domestic Air Pressure tests on these new build properties in Ullesthorpe.

The required target for Plot 5 was 5.8, while the target for Plot 4 was 5.5.

The Process

After reviewing drawings, on site testing was ready to be completed. All suitable equipment was set up and checked over to ensure the best possible result.

The Result

 

Plot 4 Target

Plot 5 Target

Result

Result

 

Pass

 

Pass

The Outcome

Both properties passed their air tests and certificates have been issued.