Project: Air Pressure Testing Enfield

Air Pressure Testing Enfield

Completed: 02/04/2018

Technician: Cameron Milne

The Brief

We were instructed to complete two Domestic Air Pressure tests on this new-build property in Enfield.

The required targets for this particular test was 5.

 

The Process

After reviewing drawings, on site testing was ready to be completed. All suitable equipment was set up and checked over to ensure the best possible result.

The Result

 

Flat 5 Target

Flat 6 Target

Flat 5 Result

Flat 6 Result

 

Pass

 

Pass

The Outcome

This building passed both tests and as a result, certificates will be issued shortly.

For more information on what is required to pass an Air tightness test click HERE