Project: Air Pressure Testing Greenwich

Completed: 12/10/2017

Technician: Cameron Milne

The Brief

We were instructed to complete two Air Pressure Tests on these London Penthouse Flats based in Greenwich

The target for each plot was 5.

The Process

After reviewing drawings, on site testing was ready to be completed. All suitable equipment was set up and checked over to ensure the best possible result.

The Result

Target Plot 22

Target Plot 23

Result

Result

PASS

PASS

The Outcome

The property passed so certificates will be issued.

For more information on what is required to pass an Air tightness test click HERE